Hydro
Stockbridge
MA
Housatonic River
Dec 2014
770
As part of the Massachusetts Clean Energy Center’s (MassCEC) effort to help upgrade existing hydropower projects across the state, Littleville Power Co. was awarded a $600,000 grant to help build the all new Stockbridge Hydro facility. This project is expected to add 22% more energy to the region's power grid. That’s 1.4 million kilowatts of electricity, up from the 1.1 million kilowatts currently produced from the existing century-old hydropower plant in that area.