Vineyard Wind, already delivering power to the grid, is among five wind projects paused by Trump administration

Date: December 22, 2025
Author: Sabrina Shankman

As of Monday morning, it wasn’t immediately clear if already-built turbines can continue to spin and deliver power.

Vineyard Wind is nearing the completion of its construction, and has been delivering power to the New England grid since the beginning of the year. During a recent cold snap, the project was already eliminating some $2 million a day in costs to ratepayers by displacing the need for additional natural gas.

The decision to pause the lease on a project that is well underway and already delivering power to the grid marks a radical departure from legal precedent, and an escalation of the administration’s effort to thwart the industry.

With this step, some of the region’s most promising clean energy projects — including one that has previously overcome delays during the first Trump administration as well as lawsuits from wind opponents, in addition to a catastrophic turbine blade collapse last year — are thrown into new turmoil. Monday’s announcement comes just weeks after a federal judge in Massachusetts vacated Trump’s day-one executive order that had blocked wind energy projects.

Like Vineyard Wind, the other projects affected by Monday’s decision had leases that were awarded and had been vetted by the Biden administration.

“Nobody has ever seen the executive branch take a hatchet to a particular industry like this executive has with offshore wind,” said Travis Annatoyn, who served as Deputy Solicitor for Energy and Mineral Resources at the US Department of the Interior during the Biden administration. “It’s remarkable, even relative to the administration’s actions on other renewable energy sources.”

In making the decision to pause the leases, the Interior Department said unclassified reports from the US government have long found that the movement of massive turbine blades and the highly reflective towers create radar interference called “clutter.” According to the Interior Department, that clutter can obscure legitimate moving targets and generate false targets near the wind the projects.

Vineyard Wind was halfway complete as of September, with the expectation that it would be complete by the end of the year, with 62 turbines generating enough clean energy to power 400,000 homes in Massachusetts, according to the developer. That’s enough to meet 5.5 percent of the state’s energy demand.

Revolution Wind, meanwhile, would generate enough power for 350,000 homes in Connecticut and Rhode Island. Together, these two projects represent a cornerstone of how the region will transition to clean energy as fossil fuel power plants are retired.

The pausing of its lease puts all of that in question, while raising questions about the state’s ability to meet its emissions reductions commitments to tackle climate change, as well as the region’s ability to meet its energy needs.

A representative for Vineyard Wind did not immediately respond to a request for comment.

Larry Chretien, executive director of the Green Energy Consumers Alliance, called the decision by the Trump administration “arbitrary, capricious, illegal, and bad energy policy.”

“The playbook is obvious. The feds want to break the finances of these projects and deter developers from even thinking of starting something new,” said Chretien. “And the feds are using our taxpayer dollars to serve the interests of the fossil fuel industries.”

This latest move against wind projects comes after months of escalating attacks on the wind industry, which had been poised for a major boom prior to Trump coming into office. It is also the first time Trump has stopped a project already delivering power.

Even before taking office, Trump had made clear that he planned to gut the industry, which he has said is expensive and inefficient, while also repeating unproven claims that offshore wind installations kill whales. Trump has also repeatedly called wind turbines “ugly.”

Since taking office, he has issued an executive order to pause leasing and permitting of offshore wind, cancelled funds for wind-related port infrastructure, ordered other projects to stop construction, and directed agencies to find ways to thwart the industry.

For two of the projects targeted on Monday — Revolution Wind and Empire Wind — this is not the first time the Trump administration has halted work.

In August, the administration ordered a work stop at Revolution Wind, then an 80-percent complete offshore wind development in Rhode Island, citing national security concerns. A federal judge in late September allowed the work to restart pending the government’s review.

Earlier in the year, the administration stopped work at New York’s Empire Wind 1 project, though construction resumed following several meetings between Governor Kathy Hochul and the Trump administration. According to the administration, Hochul had shown a willingness to “move forward on critical pipeline capacity” — an about-face following New York’s past resistance to building new fossil fuel pipelines.

Hochul’s office, however, said that no deals related to a gas pipeline were made.

Vineyard Wind has employed more than 2,800 people — both union and non-union — for various lengths of time, a company official reported in 2024.

Kyle Murray, Massachusetts program director for the advocacy group the Acadia Center, called the decision Monday an unjustified attack by this administration on clean and cheap electricity.